Case Study of Reservoir Construction - Essex

Reservoir ConstructionConstruction by Brett Plant & Earthmoving of a 50,000m2 irrigation reservoir on the site of a former gravel quarry. 

 

 

 

 

 

Reservoir Construction

The main challenge was the removal of a significant quantity of waterlogged overburden and control of substantial groundwater inflows. A controlled pumping/dewatering operation was implemented and temporary drainage channels were excavated to redirect the water. 

 

 

Reservoir AggregatesA sequenced programme of excavation works then followed to form proposed levels and contours as specified.  Clay was excavated from the basal areas and engineered to form sideliner walls, a dividing bund and a key trench. 

 

 

Reservoir Construction

Upon completion of the reservoir construction circa 100,000m3 of overburden had been removed and

circa 50,000m3 of clay had used to form an impermeable barrier to hold water.