Reservoir Construction

Construction by Brett Plant & Earthmoving of a 50,000m2 irrigation reservoir on the site of a former gravel quarry.

The main challenge was the removal of a significant quantity of waterlogged overburden and control of substantial groundwater inflows. A controlled pumping/dewatering operation was implemented and temporary drainage channels were excavated to redirect the water.

A sequenced programme of excavation works then followed to form proposed levels and contours as specified. Clay was excavated from the basal areas and engineered to form sideliner walls, a dividing bund and a key trench.

Upon completion of the reservoir construction circa 100,000m3 of overburden had been removed and circa 50,000m3 of clay had used to form an impermeable barrier to hold water.

Quick links

  • Contact Us & Site Finder

    Contact Us & Site Finder

    Southern Area - 01795 594000
    Eastern Area - 01473 811900
    London & Home Counties - 01784 263940
    More

  • Safety Health & Environment

    Safety Health & Environment

    Find out more about Brett Aggregates approach to safety, health & the environment
    more

  • Aggregates Safety Data Sheets

    Aggregates Safety Data Sheets

    Our Safety data sheets provide information regarding the properties of the particular substances used within our materials.
    Read more